Keep up to date with the Indian Ocean Marine Research Centre's development via a milestone schedule and project updates.
A number of milestones have been identified to track the project status.
| Milestone | Date | Status |
|---|---|---|
| Establish Steering Committee | April 2010 | Completed |
| EIF bid success | June 2010 | Completed |
| Establish Project Control Group | August 2010 | Completed |
| Appoint Project Manager | August 2010 | Completed |
| Appoint Project Architect | February 2011 | Completed |
| Lodgement of Development Application | November 2012 | Lodged |
| Award construction contract (Crawley) | Early 2013 | |
| Completion of Crawley | Occupation anticipated 2015 |